Bathroom Remodeling Pricing · Arizona
What a Bathroom Remodel Costs in Arizona
Real planning ranges for hall baths and primary suites in the Valley and Northern Arizona, built with custom shower pans and real waterproofing.
$20,000 to $90,000
Most of our bathroom remodels start around $20,000.
That buys a full tear-out, a custom shower pan, real waterproofing, tile, vanity and fixtures done right. We do not do $5,000 cosmetic bath flips, because the part that matters is behind the tile.
A bathroom remodel with Redeemed Builders typically costs $20,000 to $90,000 in Arizona. A hall bath kept in its existing layout sits near the lower end. A primary bath with relocated plumbing, a curbless shower and natural stone sits near the top. The biggest lever is whether the toilet, shower and vanity drains stay where they are.
Why we published this
The decision that moves the number most: where the drains go
In most Arizona homes the bathroom sits on a concrete slab. The toilet, shower and vanity drains are cast into it. When those stay where they are, the remodel is about everything above the floor: pan, waterproofing, tile, glass, vanity and fixtures.
When they move, we cut the slab. Trench, re-route, inspect, re-pour, then build back up. Swapping a tub for a bigger shower, moving the toilet into its own room, or going curbless all bring some of that work.
Often it is worth it. A cramped primary bath that finally works is a daily gift. But it is the first decision to make, because it shapes the budget more than tile or fixtures.
What moves the number
What actually drives the price
Six things move a bathroom remodel more than anything else.
Plumbing location
Keeping drains where they are saves the most. Moving them means cutting and re-pouring slab, or reworking joists on a raised floor, plus new inspections.
Shower size and type
A larger shower, a bench, multiple niches or a curbless entry each add pan work, waterproofing and tile labor. Curbless often means recessing the subfloor.
Tile
Large-format porcelain, intricate patterns and natural stone take more time to lay and more care to finish. Tile choice and layout can swing the labor line considerably.
Glass
Frameless heavy glass costs more than framed, and custom panels for unusual openings cost more than standard sizes.
Vanity and storage
A stock vanity and a custom double vanity with a tall linen tower are very different line items.
Size of the room
A primary suite has more floor, more wall tile and more fixtures than a hall bath, even with the same finishes.
Placing your project
Where your project lands in that range
Here is how real bathrooms move through the range.
Toward the lower end
Roughly $20,000 to $35,000. A hall or guest bath in its existing layout: full tear-out, custom shower pan or new tub, porcelain tile, stock or semi-custom vanity, new fixtures, lighting and an exhaust fan.
Through the middle
Roughly $35,000 to $60,000. A primary bath with a tub-to-shower conversion or larger shower, frameless glass, upgraded tile with a niche and bench, a double vanity and layered lighting.
At the upper end
Roughly $60,000 to $90,000. A re-planned primary suite with relocated plumbing, a curbless shower, natural stone, custom cabinetry, a freestanding tub and premium fixtures.
Bringing it down
What lowers the cost
If the number is higher than you hoped, here is where real savings come from.
Keep the drains
Leave the toilet, shower and vanity where they are. It is the biggest saving in the room.
Choose porcelain
Quality porcelain looks great, lays faster and costs less than natural stone. Use stone as an accent.
Use standard glass sizes
A shower designed around a standard panel width avoids custom glass costs.
Keep the tub where it is
If you use a tub, re-tiling around it in place is far simpler than moving it.
Semi-custom vanity
A good semi-custom vanity, set level and finished cleanly, looks as good as custom in most rooms.
Do two baths at once
Remodeling two bathrooms together shares mobilization, inspections and trade visits.
What to expect
Permits, lead times and living through it
Permits. Moving plumbing, adding circuits or changing walls needs a permit in Valley cities and in Yavapai and Coconino counties. Like-for-like fixture swaps often do not. We tell you which applies and handle it.
Lead times. Vanities, tile and custom glass can each take a few weeks. Glass is measured after tile is finished. We order early so the bathroom is not sitting half done.
Disruption. Plan on four to eight weeks without that bathroom, depending on scope. If it is your only shower, we talk through options before we start.
Questions
Bathroom Cost, Questions Answered
How much does a bathroom remodel cost in Arizona?
Our bathroom remodels run $20,000 to $90,000. Plumbing location, shower size, tile choice and glass account for most of the difference.
How much does a tub-to-shower conversion cost?
As part of a full remodel, most conversions land roughly between $30,000 and $55,000, spanning the lower and middle of our range, depending on size, tile and glass. Curbless conversions on a slab cost more because the floor has to be recessed.
What is a custom shower pan?
The sloped, waterproofed base under your shower tile, built on site to fit your shower exactly. We build every pan, waterproof it as a full system and flood test it before tile goes on. It is included at every tier.
Why do some contractors quote much less?
Usually because the price skips the parts you cannot see: a proper pan, full waterproofing, flood testing, permits or level framing. Those shortcuts look fine at first and fail later. Ask any bidder exactly how they waterproof the shower.
Is a curbless shower worth the cost?
For many people, yes, especially for aging in place. It costs more because the floor has to be recessed for drainage, which on a slab means cutting concrete. We will tell you what your bathroom allows.
How long does a bathroom remodel take?
Most of our bathrooms take four to eight weeks of construction. Re-planned primary suites with plumbing changes sit at the longer end.
Can I remodel two bathrooms at once?
Yes, and it often saves money by sharing trade visits, inspections and mobilization. Just make sure you keep at least one working shower in the house, or plan around it.
How do I get an exact number?
Call for a free phone ballpark, then a free site walk. You get a written Good, Better and Redeemed proposal at fixed prices. One quote, one time.
Find out what your bathroom project would cost.
Tell us what you want built. Torin will give you an honest range and tell you where the money is best spent.
The ranges on this page are 2026 planning ranges for Arizona projects, drawn from the kind of work we build in the Phoenix Valley and Northern Arizona. They are not quotes. Your project's real number is the one in your written proposal, after Torin has walked the site and you have chosen a tier. That proposal is one quote, one time: the price changes only if you change the scope.
Related reading
Other project costs in Arizona
Last updated October 2026 · Written and reviewed by Torin Stansbury, owner of Redeemed Builders · Licensed Arizona KB-1 General Contractor, AZ ROC #365545